|
|
Fast Track Projects Demand Efficiency
by Dennis
Fagent
Medtronic AVE: 3675 Unocal Place, Santa Rosa, CA
Architect: Glass Architects, Santa Rosa, CA
Contractor: Rudolf and Sletten, Santa Rosa, CA 
An efficient use of steel-braced frames and column bay spacing provided
a cost effective solution for the two most recent buildings completed
by Medtronic AVE. Medtronic AVE is a fast-growth company that needed
their building to grow as fast as they were. This project, like nearly
all projects now, demanded a fast-track construction schedule to meet
the client's exploding growth needs. In order to make the project
move at this fast pace, the contractor, Rudolf and Sletten, was selected
early in the design phase, and they provided valuable feedback to
the client regarding the cost implications of design decisions. They
also worked closely with the design team in developing the construction
schedule and implementing important design phase milestones. Having
the architect, engineers, and contractor on board from the beginning
helped to ensure against costly delays that would keep them from meeting
the tight deadlines.
The design challenges of this project were also more severe than for
a typical low rise Class A office building. The Medtronic campus is
located in very close proximity to the Rodgers Creek Fault in Santa
Rosa, California. Due to this, the structural challenge was to maintain
an efficient structural design and provide for seismic design forces
over two times greater than typical code loads. Medtronic AVE expected
a higher performance level to protect the buildings features
and contents in the event of a severe earthquake. This was accomplished
by the use of structural tube braces whose locations were inconspicuously
coordinated by the project architect, Glass Architects, and the owner.
Another design challenge for the project was Medtronic's need for
unusual floor spacing. Floor-to-floor heights for the high-tech manufacturing
facility are greater than a typical office building; with a first
to second floor height of 18 feet (to accommodate a basement with
forklift access at the ground floor level) and with second and third
floors more typical at 14 feet. Bay spacings of 32' x 32' and 24'
x 32' were chosen to accommodate Medtronic's floor space needs by
providing efficient girder and purlin spacing and minimizing interior
columns.
The use of 50 ksi steel throughout the project, combined with the
right design, resulted in a 25% more efficient steel frame than typically
experienced by the general contractor, and at a significantly lower
cost. Overall the total weight of steel for these buildings was an
economical 6 lbs. per square foot. The end result is an efficient
building meeting both the clients schedule and cost goals. |
|